Not much to tell from today. Working with wiring continues, now with this dashboard and AC loom. This needs all of the old harness tape removed and reapplied properly.
20250311_124259.jpg
Someone had "repaired" the ignition switch before
20250311_144606.jpg
I made it a little better. The best thing would be replacing the wires end to end, but I think it's good enough.
20250311_152303.jpg
S2 Avant -93
Collapse
X
-
It was a little head scratcher at first, but the masking tape and grease made it much easier than trying to pull the whole harness through the grommet without any lubrication. My cheap set of terminal removal tools was propably the worst part of this
I had broken wires right at this point of the harness that I repaired some time ago. I only wrapped them in harness tape then but since the grommet was available, I thought it was worth doing properly this time.Leave a comment:
-
That must have been a complete pain in the *** to do, worth it in the end though. Brilliant effort all round Sir.
This grommet was broken so I got a new one. Pretty hard to install on the assebled harness however. Every connector had to be depinned and then all the wiring was wrapped in masking tape and lubed. This worked out ok.
115.jpg
All the way in. This was over a two hour job. It included some fiddling with the connectors since I only have cheap tool for terminal removal.
Leave a comment:
-
-
Then I moved on to electrical stuff. Butyl cord for sealing the fuse box frame to chassis.
111.jpg
112.jpg
It's nice to have the fuse box like this. Much more comfortable working position than under the dashboard.
113.jpg
This grommet was broken so I got a new one. Pretty hard to install on the assembled harness however. Every connector had to be depinned and then all the wiring was wrapped in masking tape and lubed. This worked out ok.
115.jpg
All the way in. This was over a two hour job. It included some fiddling with the connectors since I only have cheap tool for terminal removal.
116.jpg
Then it was time to sort out the loom for doors, window lifters and central locking.
117.jpg
Looks a bit messy but hopefully it will be better when I can tie up the harness. Now I'll have to wait for the harness ties to arrive.
20250305_160029.jpgLast edited by Antsa; 5 March 2025, 19:09.Leave a comment:
-
Nice work
Note that the black screw down panel that covers the wire either side needs some tiger seal in places otherwise it will leak in heavy rain. I found out the hard way
Leave a comment:
-
Fuel pipes got sorted with few additional bends. I'm going to modify the connector bracket and add one more fuel pipe support.
1.jpg
Then it was time to move onto the sunroof. It has glue stains from headliner.
2.jpg
I attacked it with cordless drill and a toffee wheel
3.jpg
After cleaning it was time to disassemble the sunroof mechanism.
4.jpg
New slide/guide pieces
5.jpg
6.jpg
7.jpg
8.jpg
And then everything was lubed up using special grease
9.jpg
Motor installed and wired to a car battery for testing
10.jpg
And it works!
11.jpg
12.jpg
And it's in
13.jpgAttached FilesLast edited by Antsa; 5 March 2025, 16:41.Leave a comment:
-
Brake lines all finally done today. Took way much longer than I thought. Press comes in handy again for holding the flaring tool.
1.jpg
These are the lines around the front strut and behind rear lower arm. Can't install them since I don't have brake hoses yet. I will have to do a test fit on the calipers so I can measure and make an order on custom hoses.
2.jpg
Abs pump, brake booster and master cylinder in place
3.jpg
All wiring harnesses that go through the bulkhead are in place.
4.jpg
5.jpg
Pedalbox and streering column in. Pedals have new rubbers.
6.jpg
One of my front arms was missing the press fit bolt
7.jpg
So I got this (857407175)
8.jpg
The bolt was easily pressed out
9.jpg
The lengt of the knurled area is a bit short compared to the original 893407745A.
10.jpg
Here it's installed. Went in easily with the press. I quickly tried torquing a balljoint to the arm and the knurling didn't slip even if it's shorter than original.
11.jpg
Leave a comment:
-
Fuel lines installed. Just to see that I have made a mistake. The feed line is kind of in the way of the engine sub harness connector bracket. I might be able to install all the connectors to the bracket by just pulling the fuel line out of the way by hand, but I think I'm going to do a few more bends so I can get the line to run a bit higher and closer to firewall.
11.jpg
The bracket still needs a clean and paint. I will also modify it by cutting out the ingition amplifier mounting points.
22.jpg
Even though the fuel system is not completely ready, I couldn't resist doing a leak test. This test covers the section from fuel tank bulkhead to the end of the hard line in the engine bay. System got charged to 9 bar.
33.jpg
After about five hours the pressure was 8.8 bar. I'm calling this good enough. My self made test setup has two hose connections secured with jubilee clips and at least six threaded connections sealed with ptfe tape, so plenty of sources for small leak outside the fuel system itself.
44.jpg
I bought myself a 20ton press to fit the wheel bearings. Bearings were easy to install with the press, but hubs were easier to install this way. The press serves as an excellent subtitute for a vise.
55.jpg
66.jpg
All bearings and hubs in place. Mating surface for the hub and wheels is left untreated. Small touch up paint has to be done before installing.
77.jpgLast edited by Antsa; 22 February 2025, 18:55.Leave a comment:
-
Almost a month since last update
A lot of sorting out little bits and thinking of best way to go on.
At least I got the trim installed that follows the roof. ETKA calls for this 'protctive film' under the stainless clips.
1.jpg
2.jpg
The clips are riveted in place with stainless rivets
3.jpg
Trim installed
4.jpg
All driveshafts were cleaned and painted.
5.jpg
Rear shafts also got new inner GKN cv's and OE boots.
6.jpg
And installed
7.jpgLeave a comment:
-
Thanks for the info, just what I needed to hear
. Hopefully going to spray epoxy this weekend after stripping the bottom, that wasn't enjoyable.
Leave a comment:
-
Hi mate
No exact dimensions available right now, it is just right size rectangular pipe inside rear chassis rails and round pipe inside front rails. Both have 8mm thick steel plates at the end, which the vertical wooden support bolts onto
Leave a comment:
-
What a lovely jig...could you share more info regarding dimensions ? Really nice project and topicTip over jig is now completed
20240703_201656.jpg
And it works too!
20240703_194826.jpg
I also added some small wheels to it so can move it around more easily. Its a useful feature since now I can push the car outside so its out of the way if I need to clean the garage.
20240704_135656.jpg
Thats all for now. There is going to be a little break for these updates, my summer holiday is over and I have to service both daily drivers before I can get back to working on Audi
Leave a comment: